0 Comment(s) Posted

 

We had some exceptional crews this weekend. On one house, we were able to start and finish the shingles, line and crawl the plastic for the subs, and complete truss bracing. It usually takes two full Saturdays to complete the shingles- great job! We also back framed on two houses, completed 90% of the shingles on another house, did some framing details on another house, and worked on exterior walls of the last house. We stood one wall and finished the sheathing on the second long exterior wall. We will raise trusses on two houses this week, and be ready to deck these two roofs by the weekend. With the roofs complete on some houses, we will begin vinyl siding and continue wall framing. Come enjoy this warm weather with us for as long as it lasts. See you all this weekend!

 